On Monday Kez and I went to the house to meet our site supervisor for the first inspection. We were given a blue roll of tape to stick all over the house on any bits and pieces that needed a touch up.
Most of the things we found were just paint touch ups, however there were a few other bits and pieces that needed to be fixed before hand over.
- Small square on the matrix cladding of the facade needs to be sanded and painted
- Some mortar needs to be touched up on the brick work
- Kitchen cavity sliding door needs to be readjusted as it currently slides out a little crooked
- Antenna points and Cat 6 points still need to be brought out and terminated properly
- Upstairs toilet flush not working
- A few door handles need to be replaced
- Render needs to be touched up on the facade
- Still awaiting mirror splashback installation and block out blinds upstairs
As you can see in the picture, the concrete driveway is now complete although I'm not convinced the colour looks anything like what we chose (although not much we can do about it now). It's also a bit patchy in some parts so our SS has asked the concrete to come back and fix it.
Unfortunately we were too busy putting blue tape everywhere to get any photos. We should have hand over by some time next week so more pics will come! Just waiting on the occupancy certificate now and the bank needs to complete a valuation, and hopefully the keys will be ours very soon :)